Th PDC confirms a post Production EPA/CARB delivery delay on the 2013 X vehicles. They also say that this is nothing special, just the typical approval they must wait for each new model year vehicle. They also indicate that they have no control over how long it takes for the federal approval. It can take anywhere from 2-6 weeks (following the production of the first new model year vehicle).

With production starting mid-April, that would imply the very first deliveries sometime during the month of May.